Golf course bids were gathered this month. Still supposed to reopen May 2019...
Renderings:
http://iuhoosiers.com/news/2017/10/...-approves-golf-course-renovation-designs.aspx
Wilkinson Hall (wrestling and volleyball) is rising quickly and will open in September. The bid for the new videoboard just went out today:
http://distribution.easternengineering.com/Job_Details/BL600 Wilkinson Hall LED and Scoring Bid Form.xlsx
New (first season this fall) volleyball coach seems pretty good (Penn State and Maryland) so that should be fun...
A couple of weeks old:
Right now:
Webcam link if you want a non-crappy view during the day:
http://webtech.webhost.iu.edu/build/wilkinson/popup.html
Parking for football and basketball will be clear because it opens up in September:
South End Zone move in is in August...
As of late March:
2006-2018:
ADA seating has been added on both the east and west sides. Current ADA seating is being renovated, along with restrooms (troughs are out) and concessions and areas up in the press box/suites as well, to remain up to code. They removed a row of seating behind each of the four new ADA platforms as to prevent obstructed views. Two concession areas are being added on the new patio, and new restrooms as well:
Layout:
Nothing much for basketball at the moment. They’re renovating some more of the control rooms in the bowels of Assembly Hall, and I’m not sure whatever happened to plans to renovate the Assembly Hall locker room. Or if they did it already. The Cook Hall locker room is already very nice.
Armstrong Stadium is still supposed to get a $6 million renovation at some point. Haven’t heard anything on that in months.
Golf course bids were gathered this month. Still supposed to reopen May 2019...
Renderings:
http://iuhoosiers.com/news/2017/10/...-approves-golf-course-renovation-designs.aspx
Wilkinson Hall (wrestling and volleyball) is rising quickly and will open in September. The bid for the new videoboard just went out today:
http://distribution.easternengineering.com/Job_Details/BL600 Wilkinson Hall LED and Scoring Bid Form.xlsx
New (first season this fall) volleyball coach seems pretty good (Penn State and Maryland) so that should be fun...
A couple of weeks old:
Right now:
Webcam link if you want a non-crappy view during the day:
http://webtech.webhost.iu.edu/build/wilkinson/popup.html
Parking for football and basketball will be clear because it opens up in September:
South End Zone move in is in August...
As of late March:
2006-2018:
ADA seating has been added on both the east and west sides. Current ADA seating is being renovated, along with restrooms (troughs are out) and concessions and areas up in the press box/suites as well, to remain up to code. They removed a row of seating behind each of the four new ADA platforms as to prevent obstructed views. Two concession areas are being added on the new patio, and new restrooms as well:
Layout:
Nothing much for basketball at the moment. They’re renovating some more of the control rooms in the bowels of Assembly Hall, and I’m not sure whatever happened to plans to renovate the Assembly Hall locker room. Or if they did it already. The Cook Hall locker room is already very nice.
Armstrong Stadium is still supposed to get a $6 million renovation at some point. Haven’t heard anything on that in months.